San Luis Obispo · City of San Luis Obispo
SLO Airport Hotel
950 and 990 Aero Drive, San Luis Obispo, CA
The pin marks a representative location from the cited records, not a verified construction footprint. Map data © OpenStreetMap contributors.
Summary
The SLO Airport Hotel is a proposed three-story, dual-branded hotel at 950 and 990 Aero Drive, beside the San Luis Obispo County Regional Airport. The city describes it as a 127,200-square-foot building with 204 guest rooms. The environmental record describes two attached buildings of about 125,000 square feet in total, with guest amenities, a parking lot, stormwater management, landscaping and vehicle, bicycle and pedestrian access, on a 5.04-acre site.
The project began as two separate hotels proposed in 2019 and was reworked as one dual-branded building. The city released a mitigated negative declaration for design review and a use permit on April 23, 2021, with public review through May 24, 2021. A city summary of hotel projects reported by KSBY in April 2024 listed the project in building permit review with 204 rooms, and the September 2026 city tracker still lists it as under building review.
The records checked do not show a building permit issued, a construction start or an opening date.
Documented scope
- Guest rooms
- 204, dual-branded [2]
- Floor area
- 127,200 square feet, three stories (city tracker); about 125,000 square feet in two attached buildings in the 2021 environmental notice [2]
- Site area
- 5.04 acres, with about 4.33 acres of site disturbance [3]
Milestones
- City released the mitigated negative declaration for design review and a use permit (public review to May 24, 2021). [3]
- City summary reported the project in building permit review with 204 rooms. [4]
- City tracker lists the project as under building review. [2]
Dates are shown with the precision the source gives: a month or a year when the record has no exact day.
What changed
- City tracker update keeps the SLO Airport Hotel in the under-building-review list. [1]
What the records leave open
- The city tracker stage was not confirmed by a site inspection or a permit-file review. No building permit issuance, construction start or completion date is published.
- The floor area differs between the tracker (127,200 square feet) and the 2021 environmental notice (about 125,000 square feet). The date of the city's design review and use permit approval was not found in the records checked; the building-review stage implies the entitlement was granted.
- The applicant and the hotel brands are not named in the city record. Commercial listings reported in the research summary describe Hilton brands and a smaller 92-room variant, which were not verified.
More in San Luis Obispo
Sources
- Current Development Projects (City of San Luis Obispo development tracker), City of San Luis Obispo, September 21, 2026 (checked November 5, 2026) Story map shows 'Updated September 2026'; page metadata gives a September 21, 2026 modification date.
- Tracker record: SLO Airport Hotel (Under Building Review layer), City of San Luis Obispo, September 2026 (checked November 5, 2026)
- SLO Airport Hotel Project, SCH 2021040586: mitigated negative declaration notice of completion, California Office of Land Use and Climate Innovation (CEQAnet), April 23, 2021 (checked November 5, 2026)
- San Luis Obispo is experiencing a hotel boom, KSBY (news), April 2, 2024 (checked November 5, 2026) Reports a city list of hotel projects; entry: SLO Airport Hotel (950 and 990 Aero Drive), in building permit review, 204 rooms.
Research reviewed November 3, 2026. Page content reviewed November 5, 2026. Guide last updated November 5, 2026. Research last reviewed November 3, 2026; records cover November 3, 2021 to November 3, 2026. How the guide is built, and what it does not cover.
Discuss this location with a broker
Buying, selling or leasing near SLO Airport Hotel, or planning something of your own nearby? Tell us what you have in mind and we will give you a straight read on the location.
Or call 805.234.5912. You will hear back from a principal of the firm, Samuel Fox Brennan or Glenn Thomas Martin.