San Luis Obispo · City of San Luis Obispo
Prado Road Interchange
Prado Road and US Highway 101, San Luis Obispo, CA
The pin marks a representative location from the cited records, not a verified construction footprint. Map data © OpenStreetMap contributors.
Summary
The Prado Road Interchange is a planned new overpass and partial interchange on US 101 at Prado Road in San Luis Obispo, with bridge connections and bicycle and pedestrian facilities. It would let traffic cross the freeway in the middle of the city, between the Madonna Road and Los Osos Valley Road interchanges, and connect Prado Road on the east side with Dalidio Drive and the San Luis Ranch area on the west. The city is the lead agency and Caltrans must approve the project report and the environmental document.
The city filed a notice of preparation for the environmental review in February 2023 and recorded notices of determination in October and December 2024. News coverage reports that in November 2025 the council selected a preferred design, recommended that Caltrans approve the environmental document and accepted value-analysis changes that reduced the estimated cost by about $20 million. On August 4, 2026 the council approved pre-construction work, including widening the Prado Road bridge over San Luis Obispo Creek at Higuera Street to carry pedestrians and bicycles, and directed design refinements, utility undergrounding and grant applications. The city's major projects manager described the Prado projects together as about a $200 million investment.
Construction of the overpass is anticipated to begin in 2029, with the partial interchange (ramps on one side of the freeway) complete by 2031, contingent on state and federal grant funding. The Prado Creek bridge work is related but separately scheduled, and its budget should not be combined with the interchange.
Documented scope
- Facility
- New overpass and partial interchange at US 101 and Prado Road, with bridge connections and bicycle and pedestrian facilities [4]
- Schedule
- Pre-construction work approved August 2026; overpass construction anticipated to begin in 2029 and finish by 2031, subject to funding [4]
Milestones
- Notice of preparation filed for the US 101 Prado Road Interchange environmental review. [3]
- Notice of determination recorded for the project (a second notice followed on December 10, 2024). [3]
- City Council approved pre-construction work and directed design refinements, utility undergrounding and grant applications for the Prado projects. [4]
Dates are shown with the precision the source gives: a month or a year when the record has no exact day.
What changed
- Council approved pre-construction work on August 4; overpass construction set to begin in 2029 with completion by 2031. [4]
What the records leave open
- Construction is anticipated around 2029 and depends on state and federal grants that had not been awarded in the records checked. Older city material cited 2026 and is superseded.
- The November 2025 council actions (preferred design, value analysis, recommendation to Caltrans) are reported in news summaries found during research but were not opened; the city news pages return 403 to automated requests.
- Cost figures vary by source and scope: the city page gave an estimate of about $120 million for the interchange, and the August 2026 news report quotes about $200 million for the Prado projects together. They are not the same measure.
- The Prado Creek bridge widening is a separate, earlier piece of work; do not treat it as the interchange construction start.
More in San Luis Obispo
Sources
- Prado Interchange (city capital improvement project page), City of San Luis Obispo Not re-checked on November 5, 2026; date and content from the research file (construction anticipated around 2029, subject to funding and approvals). www.slocity.org returns 403 to automated requests.
- August 4, 2026 council meeting news release (Prado project directions), City of San Luis Obispo, August 7, 2026 Not re-checked on November 5, 2026; date and content from the research file. www.slocity.org returns 403 to automated requests.
- U.S. 101 Prado Road Interchange Project, SCH 2023020078: document list, California Office of Land Use and Climate Innovation (CEQAnet), December 10, 2024 (checked November 5, 2026) Lists the February 3, 2023 notice of preparation and notices of determination posted October 22 and December 10, 2024.
- San Luis Obispo's Prado Road interchange moves forward with new timeline and council approval, KSBY (news), August 6, 2026 (checked November 5, 2026)
Research reviewed November 3, 2026. Page content reviewed November 5, 2026. Guide last updated November 5, 2026. Research last reviewed November 3, 2026; records cover November 3, 2021 to November 3, 2026. How the guide is built, and what it does not cover.
Discuss this location with a broker
Buying, selling or leasing near Prado Road Interchange, or planning something of your own nearby? Tell us what you have in mind and we will give you a straight read on the location.
Or call 805.234.5912. You will hear back from a principal of the firm, Samuel Fox Brennan or Glenn Thomas Martin.