Shell Beach · City of Pismo Beach
Cliff Avenue and Ocean Boulevard storm drain repair and bluff face stabilization
Cliff Avenue and Ocean Boulevard (City right-of-way and part of Dinosaur Caves Park), Pismo Beach, CA
The pin marks a representative location from the cited records, not a verified construction footprint. Map data © OpenStreetMap contributors.
Summary
This City of Pismo Beach public works project repairs storm damage at the end of Cliff Avenue where it meets Ocean Boulevard, on the bluff next to Dinosaur Caves Park. Storms in January 2017 broke the storm drain outfall and let a sea cave begin to undermine Ocean Boulevard, the coastal trail and nearby water and sewer lines; four other damaged sites were repaired under a 2020 permit. The design, by ENGEO, includes a new 1,800-square-foot bluff wall carved and colored to match the natural bluff, 14 drilled tiebacks, 16 drilled piers 60 feet deep, a new storm drain outfall built into the wall, new curb and gutter, a six-foot sidewalk linking Margo Dodd Park with Dinosaur Caves Park, relocation of part of the trail around the sea cave, and new railings.
The Planning Commission approved the coastal development permit (P24-000073) on May 27, 2025. The work is within the Coastal Commission's appeal area. A single $8.9 million bid received in October 2025, far above the $3 million estimate, was rejected on November 18, 2025 and the plans were revised. On August 4, 2026 it awarded a $6,031,914 construction contract to John Madonna Construction, the lowest of three bids. The total project cost is estimated at about $7.33 million, most of it reimbursed through the Federal Highway Administration's Emergency Relief program with a City match.
The notice to proceed set work to begin September 21, 2026, and the City's October 2026 capital report lists the project under construction. A separate utility undergrounding project at the same intersection was completed in September 2026, and the City plans to pave angled parking along the south side of Cliff Avenue after this project finishes, in fall 2028.
Documented scope
- Bluff wall
- 1,800 square feet, 1-foot architectural face colored and textured to match the bluff, with 14 drilled tiebacks [3]
- Piers
- 16 concrete and steel reinforced drilled piers, 3 feet in diameter and 60 feet deep, spaced 8 feet on center [3]
- Trail and street
- New 6-foot sidewalk from Margo Dodd Park to Dinosaur Caves Park, trail rerouted around the sea cave, new curb and gutter, guardrail and 42-inch railing [3]
- Storm drain
- Repair and partial replacement of the storm drain inlet and outfall, built into the new wall [3]
- Construction contract
- $6,031,914, John Madonna Construction Co., Inc.; engineering services during construction up to $350,000 (ENGEO); construction management up to $948,430.61 (Cannon) [1]
- Total estimated cost and funding
- $7,330,344.61; $7,726,200 in federal Emergency Relief construction funding granted to date, reimbursed at 88.53 percent with an 11.47 percent City match [1]
Milestones
- Storm events damaged the bluff, roadway and storm drain outfall. [1]
- City Council awarded ENGEO a contract for engineering and environmental services for the Cliff Avenue and Ocean Boulevard storm drain work. [7]
- Planning Commission adopted Resolution PC-R-2025-012 approving coastal development permit P24-000073 and Categorical Exemption 2025-012, 4 to 0 with one absent. [4]
- Single construction bid of $8,943,175 received against a $2,993,930 engineer's estimate. [5]
- City Council rejected all bids. [5]
- City Council awarded Cannon Corporation a construction management contract of up to $948,430.61. [6]
- Three bids received, from $6,031,914 to $7,646,781. [1]
- City Council awarded the $6,031,914 construction contract to John Madonna Construction and accepted $4,837,540 in additional federal grant funds. [1]
- Notice to proceed date for the start of construction. [2]
Dates are shown with the precision the source gives: a month or a year when the record has no exact day.
What changed
- City capital report lists the project under construction; notice to proceed issued for work to begin September 21, 2026. [2]
- City Council awarded the $6.03 million construction contract to John Madonna Construction after rebidding. [1]
- City Council rejected the single $8.9 million bid and ordered a constructability review before rebidding. [5]
What the records leave open
- The construction start is documented by the notice to proceed date in the City's October 2026 report, not by an inspection or progress report; the state of work on site was not verified.
- The permit is within the Coastal Commission appeal area; no appeal was found, but the search was not exhaustive.
- The minutes recording the May 27, 2025 approval are draft minutes reproduced in a later agenda packet.
- Earlier versions of this page used the research file's name for the project; the scope is the same.
More in Shell Beach
Sources
- Award of Contracts to Madonna Construction and ENGEO for the Federally Funded Cliff Avenue/Ocean Boulevard Storm Drain Repair and Bluff Face Stabilization Project, City Council staff report, Item 9.E, City of Pismo Beach, August 4, 2026 (checked November 5, 2026)
- Capital Improvement Program Semi-Annual Report, City Council staff report, Item 12.A, City of Pismo Beach, October 6, 2026 (checked November 5, 2026)
- Coastal Development Permit for the enhancement and protection of the public coastal trail, street and utilities along Ocean Boulevard and Cliff Avenue (P24-000073), Planning Commission staff report, Item 7.B, City of Pismo Beach, May 27, 2025 (checked November 5, 2026)
- Draft minutes of the May 27, 2025 Planning Commission meeting (June 10, 2025 agenda packet, Item 5.A), City of Pismo Beach, June 10, 2025 (checked November 5, 2026)
- Reject All Bids Received for the Cliff Avenue/Ocean Boulevard Storm Drain Repair and Bluff Face Stabilization Project, City Council staff report, Item 9.J, City of Pismo Beach, November 18, 2025 (checked November 5, 2026)
- City Council agenda, March 17, 2026 (Item 9.F, construction management contract with Cannon Corporation), City of Pismo Beach, March 17, 2026 (checked November 5, 2026)
- City Council agenda, May 2, 2023 (Item 12.C, contract with ENGEO for the Cliff Avenue and Ocean Boulevard storm drain design), City of Pismo Beach, May 2, 2023 (checked November 5, 2026)
Research reviewed November 3, 2026. Page content reviewed November 5, 2026. Guide last updated November 5, 2026. Research last reviewed November 3, 2026; records cover November 3, 2021 to November 3, 2026. How the guide is built, and what it does not cover.
Discuss this location with a broker
Buying, selling or leasing near Cliff Avenue and Ocean Boulevard storm drain repair and bluff face stabilization, or planning something of your own nearby? Tell us what you have in mind and we will give you a straight read on the location.
Or call 805.234.5912. You will hear back from a principal of the firm, Samuel Fox Brennan or Glenn Thomas Martin.