Summary

The Halcyon Complete Streets Project rebuilds about 1.2 miles of Halcyon Road in Arroyo Grande as a street for all users. The city's description includes sidewalk repairs and infill of sidewalk gaps, replacement of trees that damage the concrete and new street trees, a road diet that reduces the number of vehicle lanes, bicycle lanes in both directions along the whole length of Halcyon Road, repaving, underground storm drain work, and a roundabout replacing the traffic signal at Halcyon Road and Fair Oaks Avenue. More than 100 on-street parking spaces, mostly north of Grand Avenue, are being removed to make room for the bike lanes.

The concept dates from 2013, the conceptual plan was adopted by the City Council on July 25, 2023 with a mitigated negative declaration, and the council reviewed the 30 percent design on February 25, 2025. The California Transportation Commission allocated about $8 million for construction on March 19, 2026, mostly from the state Active Transportation Program; half of the roundabout is funded by development impact fees. The council awarded the construction contract on June 23, 2026 and the preconstruction meeting was held July 7, 2026.

As of October 28, 2026 the city reported the storm drain line from south of Grand Avenue to north of Fair Oaks complete, concrete repairs under way starting between Grand and Fair Oaks, and Dodson Way east of Halcyon closed at Halcyon for about two weeks from October 29, 2026 for a new cross gutter. The plans allow completion at the end of summer 2027 so that the roundabout can be built while school is out.

Documented scope

Corridor
About 1.2 miles of the 1.7-mile Halcyon Road corridor [2]
Elements
Sidewalk repairs and infill, street trees, road diet, bike lanes both directions, repaving, storm drain, roundabout at Fair Oaks Avenue [1]
Construction funding
About $8 million allocated by the California Transportation Commission on March 19, 2026, mostly state Active Transportation Program [1]
Parking removed
More than 100 on-street spaces, mostly north of Grand Avenue [1]
Completion allowed
End of summer 2027 [1]

Milestones

  1. City Council adopted the conceptual Halcyon Complete Streets plan. [1]
  2. Notice of Determination posted for the project's mitigated negative declaration. [2]
  3. City Council reviewed the 30 percent design. [1]
  4. California Transportation Commission allocated about $8 million for construction. [1]
  5. City Council awarded the construction contract. [1]
  6. Preconstruction meeting held. [1]
  7. Storm drain line from south of Grand Avenue to north of Fair Oaks Avenue completed. [1]
  8. Dodson Way east of Halcyon closed at Halcyon for about two weeks for a new cross gutter. [1]

Dates are shown with the precision the source gives: a month or a year when the record has no exact day.

What changed

  • City status: storm drain components finished before the first major storm of October 22; concrete repairs continuing for several weeks; Dodson Way closure from October 29. [1]

What the records leave open

  • The contractor and contract amount are not named on the city project page and were not verified in the council record.
  • Construction completion is a planning allowance (end of summer 2027), not a confirmed date.

Related projects and phases

More in Arroyo Grande

All Arroyo Grande projects

Sources

  1. Halcyon Complete Streets Project (city project page, status as of October 28, 2026), City of Arroyo Grande, October 28, 2026 (checked November 5, 2026)
  2. Halcyon Road Complete Streets Project, Notice of Determination, SCH 2023050616, City of Arroyo Grande via CEQAnet, October 25, 2023 (checked November 5, 2026)

Research reviewed November 3, 2026. Page content reviewed November 5, 2026. Guide last updated November 5, 2026. Research last reviewed November 3, 2026; records cover November 3, 2021 to November 3, 2026. How the guide is built, and what it does not cover.

Discuss this location with a broker

Buying, selling or leasing near Halcyon Complete Streets, or planning something of your own nearby? Tell us what you have in mind and we will give you a straight read on the location.

Or call 805.234.5912. You will hear back from a principal of the firm, Samuel Fox Brennan or Glenn Thomas Martin.